
> Can be calculated using the EAC and assuming different scenarios. What is the amount of expected cost at the completion of the project?.For the forecasting of future project performance, EACĪnd TCPI the indicators of choice. However, these indicators focus on the pastĪnd current situation. Performance index (SPI) and the cost performance index (CPI).
The course of a project you usually want to knowīoth questions can be answered using the schedule
When you are in doing project controlling in The Overall Concept of Cost and Schedule Forecasting
Example 2 – Calculated with the CPI/SPI-based Approach. Example 1 – Calculated with the CPI/SPI-based Approach. (CPI) and Schedule Performance Index (SPI) 4) Calculating the EAC with the Present Cost Performance Index. Example 2 – Extrapolation of the Current Cost Variance. Example 1 – Extrapolation of the Current Cost Variance. 3) Calculating the EAC with the Present Cost Variance (CV). Example 2 – Forecast with the Budgeted Rate. Example 1 – Forecast with the Budgeted Rate. 2) Calculating the EAC Assuming that the Project will Perform. Example 2 – Calculated with an Estimate to Complete. Example 1 – Calculated with an Estimate to Complete. 1) Calculating the EAC with an Estimate to Complete (ETC). Example 2) Project ahead of Schedule with Lower Cost than. Example 1) Project behind Schedule with Cost Overrun. What is the Estimate at Completion (EAC)?. The Overall Concept of Cost and Schedule Forecasting.